Hamlet Storage
204 MW storage in Frio, TX · In queue since November 2024 · Proposed COD September 2029
204 MW
Capacity
1
Components
Battery
1y 6m
In Queue
Facility Study
IA Status
COD target: 2029
Total Duration
4y 10m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-09-04
Hamlet Storage is a proposed 204 MW battery storage project located in Frio County, Texas. Developed by Hamlet Solar, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0363, with a queue entry date of November 19, 2024. The proposed commercial operation date is September 4, 2029, and the project's interconnection agreement status is currently in the Facility Study phase.
The point of interconnection for Hamlet Storage is Tap 138kV #5895 PEARSALL -#5827 MOORE. Recent news coverage has discussed the development project.
Generated from interconnection queue and public data sources
State
TX
County
Frio
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Hamlet Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV #5895 PEARSALL -#5827 MOORE
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.