Velado Solar
96 MW generation in Dimmit, TX · In queue since November 2024 · Proposed COD September 2028
96 MW
Capacity
1
Components
Solar
1y 6m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
3y 10m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-14
Velado Solar is a proposed 96 MW solar generation project located in Dimmit County, Texas. The project, developed by Velado Solar, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0373, with a queue entry date of November 19, 2024. The proposed commercial operation date is September 14, 2028, and the project's interconnection agreement status is currently in the Facility Study phase.
The proposed project consists of 96 MW of solar photovoltaic generation. The point of interconnection is Tap 138kV 78281 Dimmit - 8274 Conoco Chittam. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Dimmit
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Velado Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 78281 Dimmit - 8274 Conoco Chittam
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- CARRIZO_ESR1
- POI Substation
- Dimmit Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.