Velado Storage
96 MW storage in Dimmit, TX · In queue since November 2024 · Proposed COD September 2028
96 MW
Capacity
1
Components
Battery
1y 6m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
3y 10m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-14
Velado Storage is a proposed 96 MW battery storage project located in Dimmit County, Texas. Developed by Velado Storage, LLC, the project entered the ERCOT interconnection queue as ERCOT-27INR0374 on November 19, 2024. The current interconnection status is listed as Facility Study, with a proposed commercial operation date of September 14, 2028.
The project consists of 96 MW of battery storage capacity. The point of interconnection is Tap 138kv 78281 Dimmit - 8274 Conoco Chittam. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Dimmit
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Velado Storage, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kv 78281 Dimmit - 8274 Conoco Chittam.
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- CARRIZO_ESR1
- POI Substation
- Dimmit Substation