Buck Ranch Solar SLF
45 MW generation in Live Oak, TX · In queue since December 2024 · Proposed COD August 2028
45 MW
Capacity
1
Components
Solar
1y 5m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
3y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-08-02
The Buck Ranch Solar SLF project is a proposed 45 MW solar generation facility in Live Oak County, Texas. Developed by Buck Ranch Solar, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0375, with a queue entry date of December 19, 2024. The proposed commercial operation date is August 2, 2028, and the project's interconnection status is currently in the Facility Study phase.
The project consists of 45 MW of solar photovoltaic generation. The point of interconnection is the 5690 WEST GEORGE WEST SUB 69kV substation. The Buck Ranch Solar SLF project has appeared in recent news coverage regarding renewable energy development in Texas.
Generated from interconnection queue and public data sources
State
TX
County
Live Oak
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Buck Ranch Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
5690 WEST GEORGE WEST SUB 69kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- West George West Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Buck Ranch Solar SLF