Buck Ranch Storage SLF
40.8 MW hybrid in Live Oak, TX · In queue since January 2025 · Proposed COD August 2028
40.8 MW
Capacity
0
Components
1y 4m
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 7m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-08-09
The Buck Ranch Storage SLF project is a proposed 40.8 MW hybrid battery energy storage project located in Live Oak County, Texas. Developed by Buck Ranch Solar, LLC, the project entered the ERCOT interconnection queue as entry ERCOT-27INR0376 on January 28, 2025. The proposed commercial operation date is August 9, 2028.
The project is currently listed as active in the ERCOT queue. It is a hybrid project consisting of battery energy storage and another unspecified technology. The point of interconnection is the 5690 WEST GEORGE WEST SUB 69kV substation.
Generated from interconnection queue and public data sources
State
TX
County
Live Oak
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Buck Ranch Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
5690 WEST GEORGE WEST SUB 69kV
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- West George West Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.