Vista Bluff Wind 1
290.4 MW generation in Upton, TX · In queue since September 2024 · Proposed COD December 2027
290.4 MW
Capacity
1
Components
Wind
1y 8m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
3y 3m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
Vista Bluff Wind 1 is a proposed wind generation project located in Upton County, Texas, with a total capacity of 290.4 MW. The project, being developed by Terra-Gen Development Company, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0377, with a queue entry date of September 4, 2024. The proposed commercial operation date is December 31, 2027. The project's interconnection status is currently in the Facility Study phase.
The point of interconnection is the Double Tap 345kV Bearkat 59903 - 76000 McCamey Ckt 1 & 2. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Upton
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Terra-Gen Development Company, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Double Tap 345kV Bearkat 59903 - 76000 McCamey Ckt 1 & 2
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- 1
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Vista Bluff Wind 1