Sugaree Solar
251.4 MW generation in Maverick, TX · In queue since October 2024 · Proposed COD September 2028
251.4 MW
Capacity
1
Components
Solar
1y 7m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
3y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-21
Sugaree Solar is a proposed solar generation project located in Maverick County, Texas, with a total capacity of 251.4 MW. The project, developed by Sugaree Solar LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0389, with a queue entry date of October 10, 2024. The proposed commercial operation date is September 21, 2028.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the 138kV line from Escondido (8260) to Brackettville (8252). The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Maverick
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Sugaree Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
138kV Escondido (8260) to Brackettville (8252)
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- Río Escondido
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Sugaree Solar