Diamond Sage Solar 2
213.96 MW generation in Webb, TX · In queue since January 2025 · Proposed COD October 2028
213.96 MW
Capacity
0
Components
1y 4m
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 9m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-10-01
Diamond Sage Solar 2 is a proposed 213.96 MW solar generation project located in Webb County, Texas. The project, developed by DGC Renewables, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0395, with a queue entry date of January 28, 2025. The proposed commercial operation date is October 1, 2028.
The project will utilize photovoltaic solar technology and interconnect at Tap 345kV LOBO7A (80219) - FOWLERTONSW5 (5709). The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Webb
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
DGC Renewables, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV LOBO7A (80219) - FOWLERTONSW5 (5709)
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.