Kresge Land Battery Storage
200 MW hybrid in Galveston, TX · In queue since March 2025 · Proposed COD June 2027
200 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
COD target: 2027
Total Duration
2y 3m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-06-01
The Kresge Land Battery Storage project is a proposed 200 MW hybrid battery energy storage project located in Galveston County, Texas. Developed by Kresge Land Battery Storage LLC, the project entered the ERCOT interconnection queue as entry 27INR0416 on March 24, 2025. The proposed commercial operation date is June 1, 2027.
The project is planned for interconnection at the 138 kV Nighthawk Substation (Bus #38985). As a hybrid project, it combines battery energy storage with another unspecified technology. The project is currently listed as active in the ERCOT interconnection queue.
Generated from interconnection queue and public data sources
State
TX
County
Galveston
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Kresge Land Battery Storage LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
138 kV Nighthawk Substation (Bus #38985)
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- Substation 41
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.