Lyra Solar
500 MW generation in Borden, TX · In queue since March 2025 · Proposed COD September 2027
500 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
Signed Jul 2025
Queue → IA
4 months
IA → COD
2y 2m
Total Duration
4 months
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-09-15
The Lyra Solar project is a proposed 500 MW solar generation project located in Borden County, Texas. The project, developed by Juno Solar 4, consists of photovoltaic solar technology. It is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0434, with a queue entry date of March 24, 2025.
The proposed commercial operation date for Lyra Solar is September 15, 2027. The project has an executed Interconnection Agreement (IA) with an effective date of July 1, 2025. The point of interconnection (POI) is the 345kV MULESHOE substation (#59922).
Generated from interconnection queue and public data sources
State
TX
County
Borden
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Juno Solar 4
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
345kV MULESHOE (#59922)
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Top solar plant owners in the US
Data tables and metrics from the powerplantsinfo.org database.
Compare Texas vs California solar
Summary analysis with parallel narrative sections and visualizations.
Top 10 solar states
Data tables and metrics from the powerplantsinfo.org database.