Clairemont Solar 1
251.75 MW generation in Kent, TX · In queue since January 2025 · Proposed COD February 2029
251.75 MW
Capacity
0
Components
1y 4m
In Queue
—
IA Status
Signed Nov 2025
Queue → IA
10 months
IA → COD
3y 3m
Total Duration
10 months
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2029-02-13
The Clairemont Solar 1 project is a proposed 251.75 MW solar photovoltaic generation project located in Kent County, Texas. Developed by Clairemont Solar LLC, the project entered the ERCOT interconnection queue on January 28, 2025, under queue ID ERCOT-27INR0435. An Interconnection Agreement (IA) was executed on November 24, 2025.
The proposed commercial operation date (COD) for Clairemont Solar 1 is February 13, 2029. The point of interconnection (POI) is the 59908 Novaprime 345kV substation. The project is currently listed as active in the ERCOT queue.
Generated from interconnection queue and public data sources
State
TX
County
Kent
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Clairemont Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
59908 Novaprime 345kV
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Clairemont Solar 1