Moon Chapel Wind
379.2 MW generation in Tom Green, TX · In queue since February 2025 · Proposed COD October 2028
379.2 MW
Capacity
0
Components
1y 3m
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-10-01
The Moon Chapel Wind project is a proposed 379.2 MW wind generation facility in Tom Green County, Texas. Developed by Orsted Onshore Development North America, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0445, with a queue entry date of February 14, 2025. The proposed commercial operation date is October 1, 2028.
Recent news coverage has discussed the Moon Chapel Wind project, with articles categorized under hazards and industry.
Generated from interconnection queue and public data sources
State
TX
County
Tom Green
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Orsted Onshore Development North America, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 76090 Divide - 76009 Twin Buttes Ckt 1
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- CALLAHA_WND1
- POI Substation
- Callahan Divide Wind Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.