Dairyland Storage
301.8 MW hybrid in Hopkins, TX · In queue since April 2025 · Proposed COD April 2029
301.8 MW
Capacity
0
Components
1y 1m
In Queue
—
IA Status
COD target: 2029
Total Duration
4 years
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-04-30
The Dairyland Storage project is a proposed 301.8 MW hybrid battery energy storage project located in Hopkins County, Texas. The developer is ENGIE IR Holdings LLC. This project is listed in the ERCOT interconnection queue as entry ERCOT-27INR0451, with a queue entry date of April 21, 2025, and a proposed commercial operation date of April 30, 2029. The point of interconnection is to the 345 kV Birthright Station (#11684).
The Dairyland Storage project has been the subject of recent news coverage, specifically regarding deals related to the project.
Generated from interconnection queue and public data sources
State
TX
County
Hopkins
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
ENGIE IR Holdings LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
To 345 kV Birthright Station (#11684)
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.