Moccasin Storage
603.08 MW hybrid in Jones, TX · In queue since January 2025 · Proposed COD July 2028
603.08 MW
Capacity
0
Components
1y 4m
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 6m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-07-01
The Moccasin Storage project is a proposed 603.08 MW hybrid development project located in Jones County, Texas. The project, developed by ENGIE IR Holdings LLC, consists of battery energy storage and another unspecified technology. It is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0452, with a queue entry date of January 28, 2025, and a proposed commercial operation date of July 1, 2028.
The point of interconnection (POI) for Moccasin Storage is Tap 345kV #60707 Kirchhoff - #60515 Clear Crossing CKT-2.
Generated from interconnection queue and public data sources
State
TX
County
Jones
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
ENGIE IR Holdings LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV #60707 Kirchhoff - #60515 Clear Crossing CKT-2
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.