Kickstart Energy Storage II
1.44 MW hybrid in Ellis, TX · In queue since March 2025 · Proposed COD September 2029
1.44 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
COD target: 2029
Total Duration
4y 6m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-09-30
Kickstart Energy Storage II is a proposed 1.44 MW hybrid energy project in Ellis County, Texas, being developed by Kickstart Infrastructure LLC. The project, consisting of battery energy storage, is located within the ERCOT region and has been assigned queue ID ERCOT-27INR0470.
The project entered the ERCOT interconnection queue on March 24, 2025, with a proposed commercial operation date of September 30, 2029. The point of interconnection is Tap 345 kV 1907 Venus Switch - 3383 BYNUM_5. The project's interconnection status is currently listed as active.
Generated from interconnection queue and public data sources
State
TX
County
Ellis
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Kickstart Infrastructure LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345 kV 1907 Venus Switch - 3383 BYNUM_5
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.