Borden Dino BESS
60.26 MW hybrid in Borden, TX · In queue since April 2025 · Proposed COD July 2028
60.26 MW
Capacity
0
Components
1y 1m
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 3m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-07-01
The Borden Dino BESS project is a proposed 60.26 MW hybrid battery energy storage project located in Borden County, Texas. The developer is Borden Dino Solar, LLC. It is listed in the ERCOT interconnection queue as entry ERCOT-27INR0481, with a queue entry date of April 1, 2025.
The proposed commercial operation date for the Borden Dino BESS project is July 1, 2028. The point of interconnection is the 59905 FARADAY 345KV substation. The project is currently listed as active in the ERCOT queue.
Generated from interconnection queue and public data sources
State
TX
County
Borden
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Borden Dino Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
59905 FARADAY 345KV
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- Faraday Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Borden Dino BESS