Power Lane II Gas
104.39 MW generation in Hunt, TX · In queue since June 2025 · Proposed COD June 2027
104.39 MW
Capacity
0
Components
11 months
In Queue
—
IA Status
COD target: 2027
Total Duration
2 years
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-06-01
Power Lane II Gas is a proposed 104.39 MW gas-fired generation project located in Hunt County, Texas. The project, utilizing internal combustion technology, is being developed by GEUS. It is listed in the ERCOT interconnection queue as entry ERCOT-27INR0489, with a queue entry date of June 3, 2025, and a proposed commercial operation date of June 1, 2027.
The project is currently listed as active in the ERCOT queue. It has been the subject of recent news coverage, with 14 articles related to the industry, grid, regulatory, and development aspects of the project.
Generated from interconnection queue and public data sources
State
TX
County
Hunt
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
GEUS
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV Caddo Mills Explorer (11832) – Scatter Branch Sub (1818) Line via (future) GEUS_STM Substation
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.