Velociraptor BESS I
261.12 MW hybrid in Ector, TX · In queue since May 2025 · Proposed COD November 2028
261.12 MW
Capacity
0
Components
1 year
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 6m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-11-17
The Velociraptor BESS I project is a proposed 261.12 MW hybrid battery energy storage project located in Ector County, Texas. Developed by Greyhound BESS 2 LLC, the project consists of battery storage and other unspecified technologies. It is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0493, with a queue entry date of May 27, 2025.
The proposed commercial operation date for Velociraptor BESS I is November 17, 2028. The point of interconnection is the 10012 METEOR_5 Substation at 345kV. The project has appeared in recent news coverage regarding energy storage developments in Texas.
Generated from interconnection queue and public data sources
State
TX
County
Ector
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Greyhound BESS 2 LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
10012 METEOR_5 Substation 345kV
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Velociraptor BESS I