Infrakey Waco Data Park Gas 2
— generation in McLennan, TX · In queue since April 2025 · Proposed COD June 2027
—
Capacity
0
Components
1y 1m
In Queue
—
IA Status
COD target: 2027
Total Duration
2y 2m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-06-01
The Infrakey Waco Data Park Gas 2 project is a proposed gas-fired generation project with a total capacity not specified in public data. It is located in McLennan County, Texas, and is being developed by Infrakey Capital LLC. The project is interconnected within the Electric Reliability Council of Texas (ERCOT) region, queue ID ERCOT-27INR0498, with a queue entry date of April 21, 2025.
The proposed commercial operation date (COD) for the Infrakey Waco Data Park Gas 2 project is June 1, 2027. The point of interconnection (POI) is at the 252 BOSQUESW8 138kV Brazos Connection. The project utilizes gas combustion turbine technology. The interconnection agreement (IA) status is not specified in public data.
Generated from interconnection queue and public data sources
State
TX
County
McLennan
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Infrakey Capital LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
252 BOSQUESW8 138kV (Brazos Connection)
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.