Draco Solar
500 MW generation in Borden, TX · In queue since April 2025 · Proposed COD August 2027
500 MW
Capacity
0
Components
1y 1m
In Queue
—
IA Status
COD target: 2027
Total Duration
2y 4m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-08-19
The Draco Solar project is a proposed 500 MW solar generation facility in Borden County, Texas. Developed by Draco Solar LLC, the project is interconnected within the ERCOT region and has appeared in recent industry news.
The project entered the ERCOT interconnection queue as entry ERCOT-27INR0499 on April 21, 2025, with a proposed commercial operation date of August 19, 2027. The point of interconnection is Tap Long Draw (59900) – Faraday (59905) CKT 1 and LONGDRAW (59900) - GALVANI(59912) CKT 2.
Generated from interconnection queue and public data sources
State
TX
County
Borden
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Draco Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap Long Draw (59900) – Faraday (59905) CKT 1 and LONGDRAW (59900) - GALVANI(59912) CKT 2
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Top solar plant owners in the US
Data tables and metrics from the powerplantsinfo.org database.
Compare Texas vs California solar
Summary analysis with parallel narrative sections and visualizations.
Top 10 solar states
Data tables and metrics from the powerplantsinfo.org database.