Antila Solar
500 MW generation in Borden, TX · In queue since April 2025 · Proposed COD November 2027
500 MW
Capacity
0
Components
1y 1m
In Queue
—
IA Status
Signed Aug 2025
Queue → IA
4 months
IA → COD
2y 3m
Total Duration
4 months
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-11-30
Antila Solar is a proposed 500 MW solar generation project located in Borden County, Texas. Developed by Antila Solar LLC, the project is interconnected within the ERCOT region under queue ID ERCOT-27INR0500. The project entered the interconnection queue on April 21, 2025, and has a proposed commercial operation date of November 30, 2027.
The project's Interconnection Agreement (IA) date is August 13, 2025. The point of interconnection (POI) is #59916 Buck Canyon 345kV. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Borden
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Antila Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
#59916 Buck Canyon 345kV
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Top solar plant owners in the US
Data tables and metrics from the powerplantsinfo.org database.
Compare Texas vs California solar
Summary analysis with parallel narrative sections and visualizations.
Top 10 solar states
Data tables and metrics from the powerplantsinfo.org database.