Dog Star Solar I
502.6 MW generation in Taylor, TX · In queue since July 2025 · Proposed COD December 2027
502.6 MW
Capacity
0
Components
10 months
In Queue
—
IA Status
COD target: 2027
Total Duration
2y 5m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
Dog Star Solar I is a proposed 502.6 MW solar generation project located in Taylor County, Texas. The project, developed by Dog Star Solar LLC, is listed in the ERCOT interconnection queue as entry ERCOT-27INR0503, with a queue entry date of July 7, 2025. The proposed commercial operation date is December 31, 2027.
The project is currently listed as active in the interconnection queue. The point of interconnection is the 6235 ABILENE MULBERRY CREEK 345 kV substation. Recent news coverage has discussed the development project.
Generated from interconnection queue and public data sources
State
TX
County
Taylor
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Dog Star Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
6235 ABILENE MULBERRY CREEK 345 kV
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Top solar plant owners in the US
Data tables and metrics from the powerplantsinfo.org database.
Compare Texas vs California solar
Summary analysis with parallel narrative sections and visualizations.
Top 10 solar states
Data tables and metrics from the powerplantsinfo.org database.