Erika BESS
100 MW hybrid in Kaufman, TX · In queue since June 2025 · Proposed COD July 2029
100 MW
Capacity
0
Components
11 months
In Queue
—
IA Status
COD target: 2029
Total Duration
4y 1m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-07-01
The Erika BESS project is a proposed 100 MW hybrid battery energy storage project located in Kaufman County, Texas. Developed by Erika Solar, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0531, with a queue entry date of June 19, 2025. The proposed commercial operation date is July 1, 2029.
The project is a hybrid facility consisting of battery energy storage paired with another unspecified technology. The point of interconnection is Tap 345kV ELKTON 5 (#3105 ) to Tricrn1 5 (#2432). The Erika BESS project has appeared in recent news coverage regarding energy storage development in Texas.
Generated from interconnection queue and public data sources
State
TX
County
Kaufman
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Erika Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV ELKTON 5 (#3105 ) to Tricrn1 5 (#2432)
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Erika BESS