Zeus Scurry BESS
1,043.07 MW hybrid in Scurry, TX · In queue since June 2025 · Proposed COD October 2028
1,043.07 MW
Capacity
0
Components
11 months
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 4m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-10-01
The Zeus Scurry BESS project is a proposed 1043.07 MW hybrid battery energy storage project located in Scurry County, Texas. The project, developed by Zeus Scurry BESS, is interconnected within the ERCOT region and entered the ERCOT interconnection queue as entry 27INR0535 on June 5, 2025. The proposed commercial operation date is October 1, 2028, and the point of interconnection is the MHOS 345 kV Substation (#59911).
The project is listed as an active project in the interconnection queue. Recent news coverage has discussed the development.
Generated from interconnection queue and public data sources
State
TX
County
Scurry
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Zeus Scurry BESS
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
MHOS 345 kV Substation (#59911)
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- ANDMDSLR_ALL
- POI Substation
- Mhos Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.