Montezuma Storage
185.1 MW hybrid in Colorado, TX · In queue since September 2025 · Proposed COD September 2027
185.1 MW
Capacity
0
Components
8 months
In Queue
—
IA Status
COD target: 2027
Total Duration
2 years
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-09-30
The Montezuma Storage project is a proposed 185.1 MW hybrid development in Colorado County, Texas. The project, sponsored by Montezuma Storage LLC, consists of battery storage and other unspecified technologies. It is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0555, with a queue entry date of September 22, 2025, and a proposed commercial operation date of September 30, 2027.
The point of interconnection is designated as L_GLIDDE8_1Y; Bus number - 7258 138KV. The project has appeared in recent news coverage regarding energy storage projects in Texas.
Generated from interconnection queue and public data sources
State
TX
County
Colorado
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Montezuma Storage LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
L_GLIDDE8_1Y; Bus number - 7258 138KV
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.