Frizzle BESS
180.9 MW hybrid in Ward, TX · In queue since September 2025 · Proposed COD October 2027
180.9 MW
Capacity
0
Components
8 months
In Queue
—
IA Status
COD target: 2027
Total Duration
2y 1m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-10-18
Frizzle BESS is a proposed 180.9 MW hybrid battery energy storage project located in Ward County, Texas. The project, developed by Frizzle BESS, L.L.C., consists of battery energy storage and other unspecified technologies. It is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0562, with a queue entry date of September 11, 2025, and a proposed commercial operation date of October 18, 2027.
The point of interconnection for Frizzle BESS is designated as #38143, TNSLVRLEAF1, 138kV.
Generated from interconnection queue and public data sources
State
TX
County
Ward
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Frizzle BESS, L.L.C.
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
#38143, TNSLVRLEAF1, 138kV
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.