Limitless Energy Hub II
1,238.25 MW generation in Wilbarger, TX · In queue since November 2025 · Proposed COD December 2028
1,238.25 MW
Capacity
0
Components
6 months
In Queue
—
IA Status
Signed Dec 2025
Queue → IA
1 month
IA → COD
3 years
Total Duration
1 month
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 24–48 months
Proposed COD: 2028-12-01
The Limitless Energy Hub II is a proposed 1238.25 MW gas-fired combined-cycle generation project located in Wilbarger County, Texas. Developed by Limitless Energy Hub II LLC, the project is in the ERCOT interconnection queue as entry ERCOT-27INR0582, with a queue entry date of November 5, 2025. The project has an active status and a proposed commercial operation date of December 1, 2028.
An Interconnection Agreement (IA) for the project was executed on December 31, 2025. The point of interconnection (POI) is the 6111 RILEY7B Substation at 345kV.
Generated from interconnection queue and public data sources
State
TX
County
Wilbarger
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Limitless Energy Hub II LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
6111 RILEY7B Substation 345kV
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.