Prairie Phoenix Wind
297.2 MW generation in McLennan, TX · In queue since February 2026 · Proposed COD September 2027
297.2 MW
Capacity
0
Components
3 months
In Queue
—
IA Status
COD target: 2027
Total Duration
1y 7m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-09-01
The Prairie Phoenix Wind project is a proposed wind generation facility with a total capacity of 297.2 MW. Located in McLennan County, Texas, the project is being developed by Prairie Hill Wind Project LLC. It is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0607, with a queue entry date of February 25, 2026, and a proposed commercial operation date of September 1, 2027.
The point of interconnection for the Prairie Phoenix Wind project is the 3403 Lake Hall 345kV substation. The project has appeared in recent news coverage regarding renewable energy development in Texas.
Generated from interconnection queue and public data sources
State
TX
County
McLennan
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Prairie Hill Wind Project LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
3403 Lake Hall 345kV
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Prairie Phoenix Wind