Oriole BES
150.39 MW storage in Knox, TX · In queue since May 2023 · Proposed COD December 2028
150.39 MW
Capacity
1
Components
Battery
3 years
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
5y 7m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-29
The Oriole BES project is a proposed 150.39 MW battery storage project located in Knox County, Texas. It is being developed by Rolling Plains Solar and is currently active in the ERCOT interconnection queue as entry ERCOT-28INR0009, with a queue entry date of May 15, 2023. The project's proposed commercial operation date is December 29, 2028, and its interconnection agreement status is currently in the Facility Study phase.
The proposed project consists solely of battery storage, with a total capacity of 150.39 MW. The point of interconnection is Tap 345kV 6076 Foxtail - 60791 Perigee. The Oriole BES project has appeared in recent news coverage regarding energy storage development in Texas.
Generated from interconnection queue and public data sources
State
TX
County
Knox
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Rolling Plains Solar
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 6076 Foxtail - 60791 Perigee
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- GPASTURE_ALL
- POI Substation
- Foxtail Switching Station
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Oriole BES