Shamrock II Wind (ERCOT-28INR0012) — Project Summary

Queue ID
ERCOT-28INR0012
Capacity
256.62 MW
Technology
Wind
Status
suspended
Location
Crockett, TX
Region
ERCOT
Developer
IA Status

Shamrock II Wind

ERCOT-28INR0012BetaSuspendedWindERCOTLBNL

256.62 MW generation in Crockett, TX · In queue since July 2023

256.62 MW

Capacity

1

Components

Wind

2y 10m

In Queue

IA Status

Interconnection

Total Duration

2y 10m

Suspended0%
Queue EntryJul 10, 2023

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

About

The Shamrock II Wind project is a proposed 256.62 MW wind generation facility in Crockett County, Texas. The project was entered into the ERCOT interconnection queue as entry ERCOT-28INR0012 on July 10, 2023. Its current status in the queue is suspended.

The development project, located within the ERCOT region, consists of 256.62 MW of wind turbine capacity. No proposed commercial operation date or interconnection agreement (IA) status is available. The developer is not specified in the queue data.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Crockett

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Utility

Entity

ERCOT

Service Type

Data Source

LBNL

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Shamrock II Wind