Sitges Wind
300 MW generation in Motley, TX · In queue since March 2024 · Proposed COD March 2030
300 MW
Capacity
1
Components
Wind
2y 2m
In Queue
Facility Study
IA Status
COD target: 2030
Total Duration
6 years
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-03-31
Sitges Wind is a proposed 300 MW wind generation project located in Motley County, Texas. The developer is NextEra Energy Interconnection Holdings, LLC. The project is currently active in the ERCOT interconnection queue as entry ERCOT-28INR0017, with a queue entry date of March 22, 2024.
The proposed commercial operation date for Sitges Wind is March 31, 2030. Its interconnection agreement status is currently in the Facility Study phase. The point of interconnection is Tap 345kV 59904 Cottonwood to 23922 White River Ckt 2.
Generated from interconnection queue and public data sources
State
TX
County
Motley
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
NextEra Energy Interconnection Holdings, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 59904 Cottonwood to 23922 White River Ckt 2
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- Cottonwood Sub
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.