Caracara Energy Storage Center
203 MW storage in Bexar, TX · In queue since May 2024 · Proposed COD August 2028
203 MW
Capacity
1
Components
Battery
2 years
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
4y 3m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-08-01
The Caracara Energy Storage Center is a proposed 203 MW battery energy storage project located in Bexar County, Texas. Developed by FRESH AIR ENERGY II, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-28INR0020, with a queue entry date of May 9, 2024. The proposed commercial operation date is August 1, 2028, and the project's interconnection agreement status is currently in the Facility Study phase.
The project consists of 203 MW of battery storage capacity. The point of interconnection is the 5234 Hunt Lane 138kV line. The Caracara Energy Storage Center has appeared in recent news coverage regarding energy storage projects in Texas.
Generated from interconnection queue and public data sources
State
TX
County
Bexar
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
FRESH AIR ENERGY II, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
5234 Hunt Lane 138kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- Hunt Lane Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Caracara Energy Storage Center