Bluefox Solar 2
401.8 MW generation in Matagorda, TX · In queue since March 2024 · Proposed COD January 2030
401.8 MW
Capacity
1
Components
Solar
2y 2m
In Queue
Facility Study
IA Status
COD target: 2030
Total Duration
5y 10m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-01-17
Bluefox Solar 2 is a proposed solar generation project with a total capacity of 401.8 MW. The project is located in Matagorda County, Texas, within the ERCOT region. It is being developed by Industrial November Project LLC.
The project is listed in the ERCOT interconnection queue as entry ERCOT-28INR0063, with a queue entry date of March 22, 2024. The proposed commercial operation date is January 17, 2030. The project's interconnection agreement status is currently in the Facility Study phase. The point of interconnection is #8754 Zoisite 345kV.
Generated from interconnection queue and public data sources
State
TX
County
Matagorda
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Industrial November Project LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
#8754 Zoisite 345kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.