Alpujarra Solar
112.5 MW generation in Wharton, TX · In queue since September 2024 · Proposed COD May 2028
112.5 MW
Capacity
1
Components
Solar
1y 8m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
3y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-05-01
The Alpujarra Solar project is a proposed 112.5 MW solar generation facility in Wharton County, Texas. The project, developed by Greening USA Corp., is currently active in the ERCOT interconnection queue as entry ERCOT-28INR0068, with a queue entry date of September 4, 2024. The proposed commercial operation date is May 1, 2028. The project's interconnection agreement status is currently in the Facility Study phase.
The point of interconnection for the Alpujarra Solar project is the 5521 GALOW 138 KV substation. Recent news coverage has discussed the development project.
Generated from interconnection queue and public data sources
State
TX
County
Wharton
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Greening USA Corp.
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
5521 GALOW 138 KV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW