Mirando Valley Wind
351 MW generation in Jim Hogg, TX · In queue since August 2024 · Proposed COD July 2028
351 MW
Capacity
1
Components
Wind
1y 9m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
3y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-07-06
The Mirando Valley Wind project is a proposed 351 MW wind generation facility in Jim Hogg County, Texas. The project, being developed by ACE DevCo NC LLC, is located within the ERCOT region and interconnected to the grid at Tap 345kV 80220 Cenizo - 80079 Cruce Ckt-1.
The project is listed in the ERCOT interconnection queue as entry ERCOT-28INR0072, with a queue entry date of August 16, 2024. Its proposed commercial operation date is July 6, 2028, and its interconnection agreement status is currently in the Facility Study phase.
Generated from interconnection queue and public data sources
State
TX
County
Jim Hogg
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
ACE DevCo NC LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 80220 Cenizo - 80079 Cruce Ckt-1
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- Cenizo Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.