Red Hollow Renewable Energy Solar SLF
308.6 MW generation in Archer, TX · In queue since July 2024 · Proposed COD September 2028
308.6 MW
Capacity
1
Components
Solar
1y 10m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
4y 2m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-18
Red Hollow Renewable Energy Solar SLF is a proposed solar generation project located in Archer County, Texas, with a total capacity of 308.6 MW. Developed by Red Hollow Renewable Energy LLC, the project is interconnected within the ERCOT region and has appeared in recent industry news. The project, identified by queue ID ERCOT-28INR0088, entered the ERCOT interconnection queue on July 1, 2024, and has a proposed commercial operation date of September 18, 2028. Its interconnection status is currently in the Facility Study phase.
The proposed project consists of 308.6 MW of solar photovoltaic generation. The point of interconnection is at Tap 345kV (Bus# 1422) Bowman - (Bus# 17002) Garvey Road.
Generated from interconnection queue and public data sources
State
TX
County
Archer
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Red Hollow Renewable Energy LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV (Bus# 1422) Bowman - (Bus# 17002) Garvey Road
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-14