Starlit Pasture Storage (ERCOT-28INR0095) — Project Summary

Queue ID
ERCOT-28INR0095
Capacity
208.8 MW
Technology
Battery
Status
active
Location
Washington, TX
Region
ERCOT
Developer
Starlit Pasture Energy Center, LLC
IA Status
Facility Study

Starlit Pasture Storage

ERCOT-28INR0095BetaActiveBatteryERCOTLBNL + Live

208.8 MW storage in Washington, TX · In queue since August 2024 · Proposed COD September 2029

208.8 MW

Capacity

1

Components

Battery

1y 9m

In Queue

Facility Study

IA Status

COD target: 2029

Interconnection

Total Duration

5y 1m

Facilities Study50%
Queue EntryAug 16, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-09-30

About

The Starlit Pasture Storage project is a proposed 208.8 MW battery storage development in Washington County, Texas. The project is being developed by Starlit Pasture Energy Center, LLC. It is currently active in the ERCOT interconnection queue as entry ERCOT-28INR0095, with a queue entry date of August 16, 2024.

The proposed commercial operation date for the Starlit Pasture Storage project is September 30, 2029. The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the 7574 Chappell Hill 138 KV.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Washington

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Starlit Pasture Energy Center, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

7574 Chappell Hill 138 KV

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Starlit Pasture Storage