Vazlon Solar SLF
211.41 MW generation in La Salle, TX · In queue since October 2024 · Proposed COD June 2028
211.41 MW
Capacity
1
Components
Solar
1y 7m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
3y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-30
The Vazlon Solar SLF project is a proposed solar generation facility with a total capacity of 211.41 MW. Located in La Salle County, Texas, the project is being developed by Vazlon Energy LLC. It is currently in the ERCOT interconnection queue as entry ERCOT-28INR0101, with a queue entry date of October 1, 2024.
The proposed commercial operation date for the Vazlon Solar SLF project is June 30, 2028. Its interconnection status is currently in the Facility Study phase. The point of interconnection is the 8619 Encinal - 8627 Lemay Box Bay 138kV line. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
La Salle
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Vazlon Energy LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
8619 Encinal - 8627 Lemay Box Bay 138kV line
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Vazlon Solar SLF