Vast Sands Power I (TEF -Due Diligence) (ERCOT-28INR0105) — Project Summary

Queue ID
ERCOT-28INR0105
Capacity
440 MW
Technology
Gas
Status
active
Location
Ward, TX
Region
ERCOT
Developer
Permian Power I LLC
IA Status
Facility Study

Vast Sands Power I (TEF -Due Diligence)

ERCOT-28INR0105BetaActiveGasERCOTLBNL + Live

440 MW generation in Ward, TX · In queue since July 2024 · Proposed COD May 2028

440 MW

Capacity

1

Components

Gas

1y 10m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection

Total Duration

3y 10m

Facilities Study50%
Queue EntryJul 22, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-05-01

About

Vast Sands Power I (TEF -Due Diligence) is a proposed 440 MW natural gas generation project located in Ward County, Texas. The developer is Permian Power I LLC. The project is currently active in the ERCOT interconnection queue as entry ERCOT-28INR0105, with a queue entry date of July 22, 2024.

The proposed commercial operation date is May 1, 2028. The project's interconnection status is currently in the Facility Study phase.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Ward

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Permian Power I LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Tap 345kV 11010 Wolf Switch - 11188 Quarry Field Switch Ckt 2

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.