RAYBURN ENERGY STATION II Gas (TEF-Due Diligence) (ERCOT-28INR0108) — Project Summary

Queue ID
ERCOT-28INR0108
Capacity
570 MW
Technology
Gas
Status
active
Location
Grayson, TX
Region
ERCOT
Developer
Rayburn Energy Station LLC
IA Status

RAYBURN ENERGY STATION II Gas (TEF-Due Diligence)

ERCOT-28INR0108BetaActiveGasCombustion (gas) TurbineERCOTLive · ERCOT

570 MW generation in Grayson, TX · In queue since January 2025 · Proposed COD February 2028

570 MW

Capacity

0

Components

1y 4m

In Queue

IA Status

Signed Dec 2025

Interconnection

Queue → IA

11 months

IA → COD

2y 2m

Total Duration

11 months

Construction0%
Queue EntryJan 13, 2025

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementDec 22, 2025

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 24–48 months

Commercial Operation

Proposed COD: 2028-02-26

About

The Rayburn Energy Station II Gas (TEF-Due Diligence) project is a proposed 570 MW gas-fired generation project located in Grayson County, Texas. The developer is Rayburn Energy Station LLC. This project is in the ERCOT interconnection queue as entry ERCOT-28INR0108, with a queue entry date of January 13, 2025, and a proposed commercial operation date of February 26, 2028. An Interconnection Agreement (IA) was executed on December 22, 2025.

The proposed project is linked to the existing Rayburn Energy Station LLC operating plant (EIA ID 58005).

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Grayson

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Rayburn Energy Station LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Double Tap 138 kV Haggerty (12677) - Progress Park (#12678) & Haggerty - Winding Oaks Switch

Data Source

Live · ERCOT

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
HIGH
Nearest Node (Estimated)
PANDA_S_ST1

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.