Copperleaf Energy Storage
167.2 MW storage in Wichita, TX · In queue since November 2024 · Proposed COD April 2029
167.2 MW
Capacity
1
Components
Battery
1y 6m
In Queue
Facility Study
IA Status
COD target: 2029
Total Duration
4y 5m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-04-18
Copperleaf Energy Storage is a proposed 167.2 MW battery storage project located in Wichita County, Texas. The project, developed by Copperleaf Energy Storage, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-28INR0118, with a queue entry date of November 19, 2024. Its proposed commercial operation date is April 18, 2029, and its interconnection agreement status is currently in the Facility Study phase.
The proposed project consists entirely of battery storage, with a total capacity of 167.2 MW. The point of interconnection is at the 1426 FISHER ROAD SWITCH 138 kV location. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Wichita
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Copperleaf Energy Storage, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
1426 FISHER ROAD SWITCH 138 kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.