River Boat Storage
207.02 MW storage in Mitchell, TX · In queue since October 2024 · Proposed COD September 2028
207.02 MW
Capacity
1
Components
Battery
1y 7m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
3y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-25
The River Boat Storage project is a proposed 207.02 MW battery storage project located in Mitchell County, Texas. Developed by Champion Creek Storage, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-28INR0133, with a queue entry date of October 1, 2024. The proposed commercial operation date is September 25, 2028, and the project's interconnection agreement status is currently in the Facility Study phase.
The River Boat Storage project has been mentioned in recent news coverage related to grid development. The point of interconnection is Tap 345 kV Bus # 10053 Cattlemen 5 - Bus #76030 Gasconades Creek.
Generated from interconnection queue and public data sources
State
TX
County
Mitchell
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Champion Creek Storage, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345 kV Bus # 10053 Cattlemen 5 - Bus #76030 Gasconades Creek
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about River Boat Storage