Chimney Creek Solar
203.88 MW generation in Shackelford, TX · In queue since February 2025 · Proposed COD May 2030
203.88 MW
Capacity
0
Components
1y 3m
In Queue
—
IA Status
COD target: 2030
Total Duration
5y 3m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-05-30
Chimney Creek Solar is a proposed 203.88 MW solar photovoltaic generation project located in Shackelford County, Texas. The project, developed by Chimney Creek Energy, LLC, is in the ERCOT interconnection queue as entry ERCOT-28INR0151, with a queue entry date of February 14, 2025. The proposed commercial operation date is May 30, 2030.
The project is currently listed as active in the interconnection queue and has been the subject of recent news coverage related to grid development. The point of interconnection is Tap 345 kV 68000 West Shackelford – 60515 Clear Crossing Ckt 1.
Generated from interconnection queue and public data sources
State
TX
County
Shackelford
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Chimney Creek Energy, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345 kV 68000 West Shackelford – 60515 Clear Crossing Ckt 1
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26