Coke BESS
220.3 MW storage in Coke, TX · In queue since October 2024 · Proposed COD April 2028
220.3 MW
Capacity
1
Components
Battery
1y 7m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
3y 6m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-04-10
The Coke BESS project is a proposed 220.3 MW battery storage project located in Coke County, Texas. The developer is Coke ESS, LLC. It is interconnected within the ERCOT region under queue ID ERCOT-28INR0155, with a queue entry date of October 1, 2024, and a proposed commercial operation date of April 10, 2028. The project's interconnection status is currently in the Facility Study phase.
The proposed project is linked to the existing Coke BESS operating plant (EIA ID 68668). The project has been mentioned in recent news coverage related to the electric grid.
Generated from interconnection queue and public data sources
State
TX
County
Coke
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Coke ESS, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
76090 Divide Switchyard 345kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- HIGH
- POI Substation
- Divide Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Coke BESS