Neal Solar
146.6 MW generation in Wharton, TX · In queue since May 2025 · Proposed COD April 2029
146.6 MW
Capacity
0
Components
1 year
In Queue
—
IA Status
COD target: 2029
Total Duration
3y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-04-03
The Neal Solar project is a proposed 146.6 MW solar generation facility in Wharton County, Texas. The project, being developed by CH Neal Solar LLC, is interconnected within the ERCOT region under queue ID ERCOT-28INR0160. It entered the interconnection queue on May 27, 2025, with a proposed commercial operation date of April 3, 2029. The point of interconnection is at the tap of the 138kV 8750 CHARMERP4A - 8127 South Lane City line.
The Neal Solar project has been featured in recent news coverage related to the energy industry.
Generated from interconnection queue and public data sources
State
TX
County
Wharton
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
CH Neal Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap of 138kV 8750 CHARMERP4A - 8127 South Lane City
Data Source
Live · ERCOT
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Neal Solar