Savanna Prairie Solar
354.8 MW generation in Pecos, TX · In queue since October 2024 · Proposed COD June 2028
354.8 MW
Capacity
1
Components
Solar
1y 7m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
3y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-01
The Savanna Prairie Solar project is a proposed 354.8 MW solar generation facility in Pecos County, Texas. The project, being developed by Savanna Prairie Solar, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-28INR0164, with a queue entry date of October 29, 2024.
The proposed commercial operation date for the Savanna Prairie Solar project is June 1, 2028. The project's interconnection agreement status is currently in the Facility Study phase.
Generated from interconnection queue and public data sources
State
TX
County
Pecos
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Savanna Prairie Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345 kV Bus # 60404 Solstice7A - Bus # 76002 L_Bakers5_1Y
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.