Kiskadee Trail Solar SLF
406 MW generation in Dimmit, TX · In queue since October 2024 · Proposed COD March 2028
406 MW
Capacity
1
Components
Solar
1y 7m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
3y 5m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-03-01
The Kiskadee Trail Solar SLF project is a proposed 406 MW solar generation project located in Dimmit County, Texas. Developed by Kiskadee Trail Solar, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-28INR0170, with a queue entry date of October 8, 2024. The proposed commercial operation date is March 1, 2028.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is Tap 138kV 8005 Carrizo Springs - 8006 Crystal City. The Kiskadee Trail Solar SLF project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Dimmit
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Kiskadee Trail Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 8005 Carrizo Springs - 8006 Crystal City
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- Carrizo Springs Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.