Kiskadee Trail Storage SLF
406 MW storage in Dimmit, TX · In queue since October 2024 · Proposed COD March 2028
406 MW
Capacity
1
Components
Battery
1y 7m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
3y 5m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-03-01
The Kiskadee Trail Storage SLF project is a proposed 406 MW battery storage project located in Dimmit County, Texas. The developer is Kiskadee Trail Storage, LLC. It is currently in the ERCOT interconnection queue as entry ERCOT-28INR0171, with a queue entry date of October 1, 2024, and a proposed commercial operation date of March 1, 2028.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is Tap 138kV 8005 Carrizo Springs - 8006 Crystal City. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
TX
County
Dimmit
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Kiskadee Trail Storage, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV 8005 Carrizo Springs - 8006 Crystal City
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- Carrizo Springs Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.