Shoe Bar Solar
205.53 MW generation in Winkler, TX · In queue since October 2024 · Proposed COD December 2028
205.53 MW
Capacity
1
Components
Solar
1y 7m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
4y 2m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-15
The Shoe Bar Solar project is a proposed 205.53 MW solar generation facility in Winkler County, Texas. Developed by Oberon Solar V, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-28INR0178, with a queue entry date of October 29, 2024. The proposed commercial operation date is December 15, 2028.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the 138 kV Raceway Switch (Bus#18663). The Shoe Bar Solar project has appeared in recent news coverage regarding renewable energy development in Texas.
Generated from interconnection queue and public data sources
State
TX
County
Winkler
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Oberon Solar V, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
138 kV Raceway Switch (Bus#18663)
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Shoe Bar Solar