Sunburst Solar
301.6 MW generation in San Patricio, TX · In queue since October 2024 · Proposed COD March 2029
301.6 MW
Capacity
1
Components
Solar
1y 7m
In Queue
Facility Study
IA Status
COD target: 2029
Total Duration
4y 5m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-03-16
The Sunburst Solar project is a proposed 301.6 MW solar generation facility in San Patricio County, Texas. Developed by Indigo Solar, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-28INR0179, with a queue entry date of October 10, 2024.
The proposed commercial operation date for Sunburst Solar is March 16, 2029. Its interconnection status is currently in the Facility Study phase, and the point of interconnection is Tap LONHILL (Bus#8455) to KATOEN (Bus#8579). The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
San Patricio
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Indigo Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap LONHILL (Bus#8455) to KATOEN (Bus#8579).
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.